Case History

DIAL Gas Lift Enables Production Optimization and Reduces Well Intervention in Southeast Asia Onshore Field

A two well pilot of the DIAL System was implemented with an onshore operator in Southeast Asia. An in-well DIAL unit enabled continuous production optimization through monitoring key production parameters and using the information to control gas injection rate without well intervention.

Client Challenge

The candidate application was an unconventional field and the operator anticipated a rapid decline in reservoir pressure. With a conventional gas lift system, multiple flowing gradient surveys (FGS) and interventions would have been required to ensure the well was fully optimized. This equates to multiple field visits, increased OPEX expenditure, well downtime and associated HSE risk.

DIAL Solution

DIAL’s continuous pressure monitoring and surface controls offered the ideal components to safely and efficiently optimize the operator’s well performance.

Silverwell installed a DIAL unit equipped with six valves at 7,800ft MD enabling the Operator to maximize flexibility of the gas injection rate control. Pressure and temperature data from the in-well DIAL unit enabled downhole gas injection metering, which was verified against the gas injection surface flow meter throughout the pilot.

With a maximum available gas injection pressure of 1,500 psi on the surface, three gas lift stations were required to unload the well of completion fluid and reach the target gas injection depth. Reservoir and tubing pressure were sufficiently low, so gas injection could occur at the deepest possible point, just above the production packer. Conventional Injection Pressure Operated (IPO) valves and side pocket mandrels (SPM) were run above the DIAL units in station 1 and station 2 for well unloading.

The DIAL units were installed along with the Surface Control System (SCS), ¼” TEC and clamps. Silverwell also provided the services for Distributed Control System (DCS) integration. This allowed operators and production engineers to remotely monitor the well and control the DIAL System remotely, avoiding the need for wellsite visits.

To ensure the DIAL system met the installation KPIs, Periodic Flowing Gradient Surveys (FGS) were performed by the operator and verified the accuracy of the DIAL pressure and temperature sensing at depth.

Results

  1. Production Increased by up to 10%

    Interventionless adjustment of DIAL’s multi-port injection capability ensured optimum gas injection rate.

  2. Well Intervention Savings

    Six well intervention savings were identified compared to a conventional gas lift system within the first 700 days of operation, resulting ~$100K OPEX savings.

  3. High Accuracy Sensing

    Pressure and temperature sensing accuracy verified within 2.5% against the Operators flowing gradient surveys.

  4. Well Stability

    DIAL tubing pressure sensor identified upper IPO valve multi-point injection. Casing pressure was subsequently lowered which stabilized the well.

  5. 1000+ Day Run Life

    DIAL System run life exceeded 1,000+ days. Well eventually pulled and converted to Rod Pump

Six well intervention savings were identified compared to a conventional gas lift system

DIAL Data

Tubing 2-7/8” 6.4 lb/ft
Casing 7”29 lb/ft
DIAL Depth 7,800 ft. MD
Bottom Hole Pressure 1,500 Psi
Bottom Hole Temp 220 °F
Casing Head Pressure 1,500 Psi
Well Head Pressure 200 Psi
Gas Lift Injection Rate 500 Mcf/Day

Image Gallery

Other Case Histories

Want to learn how DIAL can optimize your gas lifted wells?